Glen Long Ice Rink

Author: Retention - Pegah Construction Ltd. |

 

Project Name:

Glen Long Ice Rink

Type:

Renovation

Owner:

City of Toronto

Contract Type:

Prime Contractor

Gross Floor:

1,800

Location:

35 Glen Long Ave, Toronto, Ontario

Date Completed:

2022

Architect:

CIMCO Engineering

Value:

$250,000

Description:

Replacement of the Glen Long Hockey Arena slab and refrigeration system. Work involved demolition of the existing slab and in-ground refrigeration system, followed by new header trench, precise grading, insulation, new piping, new refrigeration system, and a new one-pour slab with floating form for curb. Preparation for future dasher boards was done by the City under a separate contract. Refrigeration was performed by Cimco and slab by Tri-Con. Grading tolerance was 3/8" over the 1,800 sq. ft. slab and the finished slab measured only ¼" variance over the whole ice rink.